Renewal of the airside area at Tallinn Airport

Tallinn Airport is preparing for future increases in air traffic. We are responsible for renewal of the airport's airside area.

With the project, Tallinn Airport Ltd. wants to be prepared for future increases in air traffic and improve the safety of the airport. The most demanding work will involve the renewal of the entire paved surface of the runway.

The quality standards are high. Lemminkäinen was the company that renewed the Tallinn Airport runway during 1994–1995, which has lasted in fine condition for two decades.

Diverse Delivery

As a whole, the contract covers both the planning and the execution of the project, including earthworks and paving, along with the reconstruction of storm water systems, as well as the renewal of airport technology, such as airfield ground lighting and navigation systems.

We will expand paved areas of the airport's airside area and reinforce the foundation of the existing strip area. We will also build service roads, areas for snow disposal and de-icing treatment, testing sites for aircraft engines, fire exercise and manoeuvring area for airfield maintenance equipment, as well as concrete paving and apron stands in the airside area.

Special needs at airports

Airports are always challenging locations due to the strict safety regulations. In addition, one needs to make sure that air traffic continues to flow smoothly through it all. Night-time construction is also needed: there's a window of about six hours when the airport is closed for some nights of the week for air traffic.

The project also features cutting-edge technology that is quite rare in the entire industry. Case in point: the new airport ground lighting system which will deploy only LED technology. The installation of a new LED system will dramatically reduce the customer's electricity bill.

"According to the information we have, this will be the first airport in Europe to have 100 per cent LED ground lighting system," says Hando Rannamägi, electricity expert at Lemminkäinen.

Details

Renewal of the airside area of Tallinn Airport
Tallinn Airport Ltd.
Tallinn
Estonia
2017
  • Expansion of the paved area: 73,490 square metres
  • Estimated use of asphalt: 71,000 tonnes
  • Massive earthworks will go as deep as 2.5 metres, in some places.
  • The project started in April 2016 and will end in November 2017.